Drawings & specsField photosDaily reports & logsRFIs & emailsQuotes & invoicesSpreadsheets & SOVs

How it works
Every change order is tested line by line.
A rate is not right or wrong on its own. It is reasonable or not for this contract, on this project, at this point in the schedule.
26 05 19
Conductors & cables
Submitted: 9,800 LF @ $3.53
$34,600
CO-Verified: $2.84 / LF
$27,800
Contract scope & markupSchedule & sequenceHistory: 30 projectsMarket & location data
$152,433submitted by the contractor
$121,000supported by the evidence
−$31,433adjusted to evidence (−20.6%)
Your decisionApproved amount
9 CSI lines tested on one change order
Finding
Quantity matches the drawing markups and field photos. The rate is above the $2.84 median from 30 comparable projects, so the line is adjusted by −$6,800.
Illustrative example. Figures are not live data.
Bring clarity to your next change order.
See how CO-Ver can help your team review change orders.
Book a demo →A short walkthrough with the CO-Ver team.